Endless Energy is focused on their profit only at the expense of customers. We regret hiring them instead of other company who sent a professional salesperson who knew what he was talking about.
We thought Endless Energy had better price but we have much fewer units and don't have control for each bedroom. Instead of 6days, the whole work lasted two weeks and still left unfinished.
1 ) They used minimal number of 1 technician for HVAC which caused inevitable delays from 4 days to 8 days we were not informed each time from the manager but by the technician as they were leaving for the day.
2) They significantly lack communication. Tina, salesperson, multiple times mislead us. I addressed the problems by calling to the company but they did not responded at all. For the progress of the work, we had to chase the technician.
3) They almost completely lack site or project manager's presence on the job.
Two managers shows up but they failed to introduce themselves to homeowners completely or treat them as if subordinate, and one manager(Dave) refused to talk to the homeowner's request to talk. HVAC site manager had audacity to coaching the technician not to go over remote control with home owner saying (Don't go overboard, otherwise you would be stay here forever). He also failed to show us to see the finished work for which we found faults. He also did not reply to out text asking for missing work that are necessary.
6) They left it to the homeowner to ensure the finishing of the job after 630PM instead of the site manager checking it out and present to us. Open hall in the ceiling, dust in personal belong, Ripped shower curtain that was taken away from a tween bed,ding exposing the whole bed to the excessive dust.,
6) They had poor dust control and did not reimbursed for our expense.
They failed to cover work area from dust. As the homeowner, we had to find out which room whey would work next and rushed to cover with rolls of tapes, blue paint tapes, clear vinyl, and construction trash bags. Some with shower curtains.
Project manager Dave was arrogant and rude when he came to talk to electrical team since HVAC did not come. He did not make any eye contact with my husband within feet from him but asked, with no introduction of him, my husband to add 2 to 3 more rows of bricks on the ground for the condenser as if my husband was there as his assistant or subordinate. My husband painstakingly leveled the ground and laid bricks just to speed up the work. However, those bricks were taken off by the HVAC worker since they were not needed at all.
Dave also argued and denied any reimbursement for rolls of blue tapes, vinyl drop cloths and contractor trash bags, and shower curtain torn and thrown away by the worker and consequently contaminated beddings and personal belongings on the bed.
1. Electrical team-opened up ceiling larger that 10 x 15 inches and did not seal it at all. They did not used metal-sheathed cable like our existing cables and used a vinyl electrical cable instead which is susceptible to chewing by squirrel or other rodents which may gain access to attic.
3. Insulation team took my lamp from the attic and left trash in the attic floor and they cleaned truck on my curve side and left trashes. They failed to install door sweeps and weather strips. They contaminated the garage with cellulose dust and broken cement and failed to sweep and vaccum. They did not seal the ceiling openings they made with tapes and cracked.
They threw our shoes to a big pile and broke boxes of tile and failed to come back on the next day as schedule to finish the job.. However, they used our bathroom despite my advise not to.
Endless Energy has been Endless Pain and the job is not finished after extending twice long over two weeks. read more