This is a recommendation to strongly consider NRG Energy, Inc. (nrg.com) for the acquisition of residential solar generating plants. Our achieved goal was to use a grid-tied solar plant to generate enough electrical energy/year for all appliances and other equipment on the premises, in addition to charging our next cars. We chose NRG after consulting with four Solar companies. Based upon my entire experience, it is abundantly clear that NRG employs competent, efficient, customer-centric professional staff and operations methodology to provide high quality solar generating systems that are very competitively priced.
After deciding to purchase Solar for our house (after enjoying Solar at our previous house for 10 years), I learned about NRG through perusal of internet web sites. I have no connection whatsoever with NRG and have no obligation to provide the instant Recommendation. I am capable of making the judgments shown in this Recommendation by virtue of a very long career in physics and electronic engineering product and system design that includes inventorship of more than 20 US patents. Two of these patents resulted from work in a Solar product development group at a major semiconductor company.
The only other serious offer we received was from a nationally recognized provider whose representative was knowledgeable and professional. He offered a system having high quality components (very similar to that of NRG) for a very similar price to NRG. However, his quoted system had less than half the number of 400-Watt solar panels, and the quoted placement of them would have made installation easy but performance very much sub-standard.
NRG immediately demonstrated its efficiency by adeptly performing all sales work using internet and telephone, saving the high cost of fielding sales personnel. Inasmuch as the local electric power mains provider allows a system generating capacity that is based upon demonstrated need, NRG provided cost numbers for a wide range of solar panel module quantities. All materials to be used were specified in attractive, engineering-grade documents. Also specified was performance to be expected, derived from the equipment to be installed, the property's immediate environment, and expected weather conditions.
Throughout the project, thorough and attractive drawing sets were updated as needed and submitted to the permitting authority whenever plans changed.
The installer chosen for my project was extremely reliable, hard-working, and experienced, including expertise in solar installation, electrical equipment, and wiring. He also worked skillfully with the local governmental agency (as did NRG's home office) and the electrical mains provider. He recommended and implemented system design changes that improved electrical efficiency and physical attractiveness.
Project steps:
-Quotation and contracting
-Initial site surveys by NRG and the electric power mains provider
-Initial engineering and site plan provided by NRG
-Negotiations with and final approval from electric power mains provider regarding maximum allowable solar power capacity
-NRG Engineering provided initial drawings to governmental agency and obtained permit
-Notification from electric power mains provider that service entrance must be moved
-On-site meeting with NRG installer and electric power mains provider to work out details on re-location of service entrance
-NRG Engineering modified drawings, modified permit obtained
-All materials received on site
-NRG's installer furnished all equipment and wiring, ready for electric power mains provider to transfer the service point.
-NRG's initial inspection by the permitting authority passed.
-NRG's installer built solar generating system, including interface and monitoring platform.
-Extensive testing performed
-NRG's final inspection by the permitting authority passed.
-Electric power mains provider installed Solar Power Meter, and NRG initiated operation.
Throughout the project, all NRG personnel treated me like Family, cheerfully providing status reports, technical and administrative documentation, discussed alternatives, and were always promptly available to answer questions. This included the manager for each phase of the project as well as friendly and knowledgeable representatives of each department as needed: Sales, Finance, Engineering, Permitting, and of course, the installer. Courtesy and prompt actions extended to the governmental permitting agency and electric power mains provider.
The only thing that could have been done better is to optimize the elevation angles of the solar panel modules to achieve even better performance. I forgot about this design issue until installation was underway, and it was never mentioned previously. However, the number of KW-hours per year is shown in the contract and applies to the system as installed. read more